How to convert a quote to an invoice

Keep the accepted lines and prices; change the title, number and dates; add agreed extras; take off any deposit; add how to pay. Below: a field-by-field checklist, then one job taken from quote to final invoice.

See the worked example Load the example quote

Updated 9 October 2026

The short answer: start the invoice from the quote the client accepted and keep its descriptions, quantities and prices. Then change five things: the title (Invoice), the number (the next one in your invoice sequence, with the quote number kept as a reference), the dates (an invoice date and a due date instead of a valid-until date), the extras (work the client agreed to add, each on its own line) and what has already been paid (deposits deducted). Finish with your payment details.

Quote or invoice? A quote is an offer made before the work, valid until a date. An invoice asks for payment for work done, or for an agreed stage, by a due date. A quote never goes into your books; an invoice records money a client owes you. Same job and same prices, different purpose.

What changes and what stays

Put the accepted quote next to the new invoice and work down this table one row at a time.

PartOn the quoteOn the invoice
TitleQuotationInvoice
NumberQ-2026-031INV-2026-071, the next number in your invoice series, plus “Ref. quotation Q-2026-031”
DatesQuote date and valid-until dateInvoice date and due date
ClientPrepared forBill to: the client’s legal or trading name, billing address and any purchase order number they gave you
Line itemsThe work and prices offeredThe same descriptions, quantities and prices, as accepted
ExtrasNone yetAgreed variations as separate lines, each with the date it was agreed
Deposit“25% on acceptance”The deposit already invoiced or paid, deducted on its own line
TaxRate and amountThe same rate on the same lines, tax on any extras, and your tax number if you are registered
TermsValidity, exclusions, how to acceptPayment terms, bank details or a payment link, late payment terms
Signature box“Signed to accept”Removed

Step by step

  1. Find the version the client accepted. Use the quote number, revision and date they accepted, and keep their acceptance email or signed copy with the job, next to your order confirmation. If they said yes on the phone, confirm it in writing first (confirmation wording).
  2. Copy the lines instead of retyping them. Same descriptions, quantities and unit prices. Clients and their accounts teams check an invoice against the quote line by line, and any difference holds up payment while it is queried.
  3. Give it an invoice number. Invoices run in their own sequence, separate from quotes. Keep the quote number on the invoice as a reference so the two documents can be matched later.
  4. Replace the dates. Add the invoice date and a due date written as a date (“Due 16 October 2026”), not only “14 days”.
  5. Add agreed extras as separate lines. Name each one and say when it was agreed, for example “Variation 1: extra double socket, agreed by email 18 September”. Leave out anything the client never agreed to.
  6. Deduct what has already been invoiced or paid. Show the deposit or earlier stage payments on their own line with the number of the invoice they were billed on.
  7. Check the tax. The same rate on the same lines, tax on the extras, and your VAT, GST or sales tax number if you are registered. UK VAT points are below.
  8. Add how to pay, then send it. Bank details or a payment link, then send the PDF with the amount and due date written in the email itself.

Worked example: quote, deposit invoice, final invoice

A VAT-registered fitter quotes a business client for a staff kitchen refit, invoices a 25% deposit on acceptance, does one agreed extra and invoices the balance on completion. Names, prices and dates are made up to show the method.

QUOTATION Q-2026-0312 September 2026, valid until 2 October 2026
DescriptionQtyRateAmount
Strip out existing units and worktop, remove waste1£480.00£480.00
Supply and fit base and wall units6£310.00£1,860.00
Laminate worktop, supply and fit (metres)4£95.00£380.00
Plumbing for sink and dishwasher1£420.00£420.00
Two double sockets and under-unit lighting1£560.00£560.00
Subtotal£3,700.00
VAT 20%£740.00
Total£4,440.00
Terms: 25% deposit on acceptance, balance within 14 days of completion.

The client accepts on 8 September, and you invoice the deposit the same day:

INVOICE INV-2026-0588 September 2026, ref. quotation Q-2026-031
Deposit, 25% of quotation Q-2026-031£925.00
VAT 20%£185.00
Due on receipt£1,110.00

On 18 September the client asks for one more double socket by the window and agrees £95 plus VAT by email. The work finishes on 30 September and you send the final invoice on 2 October:

INVOICE INV-2026-0712 October 2026, due 16 October 2026, ref. quotation Q-2026-031
DescriptionAmount
Quotation Q-2026-031: the five quoted lines, as quoted£3,700.00
Variation 1: extra double socket by the window, agreed by email 18 September£95.00
Less deposit invoiced on INV-2026-058 (before VAT)−£925.00
Net amount on this invoice£2,870.00
VAT 20%£574.00
Balance due by 16 October 2026£3,444.00
On the real invoice, list the five quoted lines one by one, exactly as they were on the quote.

Why the deposit comes off before VAT. The deposit invoice already charged £185 of VAT. Taking the deposit off before VAT means the final invoice charges VAT only on the part not yet invoiced, so the VAT on the two invoices adds up to the VAT on the whole job: £185 + £574 = £759, which is 20% of £3,795 (£3,700 quoted plus £95 extra). If the final invoice charged VAT on the full £3,795 and then took off the £1,110 deposit, the balance would be the same, but the two invoices together would show £944 of VAT for a job that carries £759, which is wrong for a client who reclaims VAT.

In total the client pays £1,110 + £3,444 = £4,554: the quoted £4,440 plus £114 for the extra (£95 and £19 VAT).

Can the invoice be more than the quote?

Only for extra work the client agreed to. A quote is a fixed price for the work it describes. Citizens Advice tells consumers that a trader can’t charge more than they quoted unless they explained that extra work was needed and the customer agreed to pay more, or the quoted price was an obvious mistake, and that a rise in the trader’s own costs since the quote is not a reason (Citizens Advice).

An estimate is different. It is the trader’s best guess, so the final bill can differ from it, but a consumer can dispute a bill far above it, and where no price was fixed the customer has to pay a reasonable price and no more (Consumer Rights Act 2015, s.51). In practice:

Deposits, stage payments and part-accepted quotes

VAT when you invoice a quoted job (UK)

Sources checked 9 October 2026: HMRC VAT Notice 700 (last updated 25 June 2026), VAT Act 1994 s.89, Consumer Rights Act 2015 s.51, Citizens Advice. General information, not tax or legal advice. Putting VAT on the quote itself is covered in VAT on quotes.

In accounting software

Most accounting tools have a Convert to invoice action on the quote (some call it an estimate) that copies the lines for you. The official steps for three of them: QuickBooks Online, Zoho Books and Wave. Check what comes out against the table at the top of this page: the number, the dates, the extras and the deposit are the parts a converted draft most often gets wrong.

Help pages checked 9 October 2026.

Doing it with GetQuotationMaker

Load the example quote into the quote maker below, or start your own. With Pro ($9 one-time) the quote maker downloads the same quote as an invoice PDF: the same lines, tax and totals, with an invoice number, invoice date, due date and a “Ref. quotation” line. Before you download, add each agreed extra as a line, and the deposit as a line with a minus rate, for example “Less deposit invoiced on INV-2026-058” at −925.

On the free plan, make the invoice in our free sister tool, GetInvoiceMaker, which also works without an account.

Start from an example:
Your details
PNG or JPG under 500 KB. Shown in the preview; added to the PDF with Pro.
Client details
Quote details
Line items
Subtotal0.00
Total0.00
Notes & terms
Accent colour
Live previewUpdates as you type

Pro, $9 one-time: no “Made with GetQuotationMaker” line, your logo on the PDF, and one-click invoice from any quote.

Get Pro

Questions

Can I use the quote as the invoice?

Not as it stands. A quote is an offer with a valid-until date; an invoice is a request for payment with its own number, invoice date and due date. Start from the accepted quote, then change the title, number and dates, add agreed extras and deduct any deposit.

Should the invoice number be the same as the quote number?

No. Give the invoice the next number in your invoice sequence and keep the quote number on it as a reference, for example "INV-2026-071, ref. quotation Q-2026-031". Separate sequences keep both sets of records complete.

Can an invoice be higher than the quote?

Only for extra work the client agreed to, shown as separate lines. A quote is a fixed price for the work described, and Citizens Advice tells consumers that a rise in the trader’s own costs is not a reason to charge more than the quote.

Do I need a separate invoice for the deposit?

It is the clearest way to handle it. If you are VAT registered, the deposit creates a tax point when you receive it, so the VAT on it is due then. Deduct the deposit on the final invoice and quote the deposit invoice number.

How soon after the job should I send the invoice?

As soon as the work is finished, or on the date the quote set. A VAT-registered business in the UK must normally give a VAT-registered customer a VAT invoice within 30 days of the tax point.

What if the client accepted only part of the quote?

Invoice only the accepted items. Ideally send a revised quote for those items first and get it accepted, so the invoice matches a document the client agreed to.